Selasa, 31 Mei 2011

UNIT AUXILIARY TRANSFORMER 1 x 660 MW


GENERAL PRINCIPLES

The assembly operations are under the responsibility of the Project Management Department. Definitions of the Instruction Manual are under responsibility of the Engineering Department and the corresponding operations are carried by the assembly personnel under the authority of the site foreman.
Before starting the site works, coordination between the different departments concerned (Project Management, Engineering, Production and any other) will be achieved to implement the specific site inspection plan applicable to the contract.
Before leaving, the site foreman will be informed on the inspections and checks provided for in the site plan. During on-site assembly, the site foreman will be responsible for correct implementation of the Instruction Manual on-site and for detection of any non-conforming quality to be recorded on the nonquality data sheets.
When executing the Instruction Manual defined by Engineering Department, if a value is found out of tolerance, the site foreman will notify the Project Manager who will in turn inform the Engineer Manager or his representative so that a decision is made on any further action in agreement with the departments concerned.
Installation and commissioning of the transformer may only be carried out by qualified, skilled personnel that has licensed by independent surveyor or has been approved by manufacturer and under strict observation of this Instruction Manual.
For safety reasons, do not carry out any unauthorized work, i.e. during installation, modification, commissioning and alteration of the transformer without first consulting UNINDO. The trouble-free operation of the transformer may be put at risk.
If by any case, all term above not meet with actual actualization, transformer will be out of guarantee.